HydroElectric Facilities Evaluation
California Public Utilities Commission
Challenge: Manage the public involvement process during environmental review of PG&E’s proposed sale of California’s hydroelectric system including 110 electricity-generating units located at 68 powerhouses, 99 reservoirs, 174 dams, and 145,000 acres of land.
Role: Design and implement agency and stakeholder outreach program. Conduct 18 public and 11 agency scoping meetings and manage development of all informational materials.
Result: Through effective outreach, key issues such as fisheries impacts, water diversions, protection of cultural resources, potential land development, public access and recreation, water supply, water rights, and watershed management were raised and addressed.
|