Muni-Metro Turnback Project
Bechtel Corporation
San Francisco Transportation Commission
Challenge: Ensure compliance with CEQA/NEPA mitigation measures and act as liaison with local property owners during design and construction on San Francisco's prestigious historic waterfront.
Role: Review and monitor the design and construction process to ensure that mitigation measures regarding noise, hazardous materials, and community relations are incorporated into project plans and specifications; draft and negotiate a programmatic agreement with the State Office of Historic Preservation and coordinate on-site monitoring, data collection and analysis of thousands of historic artifacts; act as liaison with adjoining property owners; and assist the City of San Francisco in responding to project inquiries.
Result: CirclePoint’s comprehensive approach contributed to an extremely smooth design and construction process. The discovery of a historic ship during tunneling led to immediate data collection and analysis and resulted in the loss of only one construction day.
|